Beaver Dam Street Reconditioning Work Set To Begin Next Week

(Beaver Dam) Beaver Dam officials are advising motorists that road construction for the 2023 Street Reconditioning Program is set to begin next week. Ten projects that will include asphalt pavement resurfacing is anticipated to begin the week of July 24th.

They are Cherokee Road from Sioux Drive to Grove Street; Cherokee Circle; Circle Drive West; Hiawatha Drive from Denning Avenue to Grove Street; Homestead Road from Hiawatha Drive to Lake Shore Drive; Industrial Drive East from Corporate Drive to East City Limits; Mohawk Circle; Mohawk Drive; Scott Street from Hiawatha Drive to North Center Street; and Sioux Drive.

Access to the project areas will be limited during construction hours, which is 7am to 7pm weekdays, but will be maintained to the greatest extent possible during off hours. Driveway access will be available at the end of each day.

Work is slated to be completed by September 30th.